7 April 2009

Game progression was discussed further. Additional integration of the game with the Wii Fit has started.

14 April 2009.

IRB work has continued. Several issues were discussed and addressed with the IRB process and forms. Additionally, we have discussed our summer goals.

21 April 2009

We have created our summer timeline and schedule. The IRB forms have been completed and submitted. We have started to collect the materials needed to prototype our modifications for the Wii Fit Balance Board.